Sunday, 22 July 2018

Works near Chedworth - rail clearup has started

The Network Rail works next to Chedworth ground to a halt a while ago when the main contractors Carillion went into bankruptcy. The good news is that Network Rail's new contractor is now on site for the remaining 4 weeks  or so of work, so we hope to see an improvement there soon.

On the project to electrify the main line, the Besom Lane temporary compound just across the footbridge from Shire Way is expected to remain until February 2019.

Monday, 11 June 2018

Works near Chedworth - less mud but rail clearup delayed

We're glad to see that there is visibly less mud on Westerleigh Road from the tipping at Beech Hill Farm. The road is generally being kept pretty clear, though there have been occasional lapses.

On the Chedworth side the Network Rail works are still at a standstill following main contractors Carillion going into bankruptcy. The good news is that Network Rail have appointed a contractor for the remaining 4 weeks work, so we hope to see an improvement there soon.

On the the project to electrify the main line, the Besom Lane temporary compound just across the footbridge from Shire Way is expected to remain until February 2019.

Friday, 19 January 2018

Carillion collapse has effects close to home

The Carillion site at Westerleigh Road near Chedworth

The collapse of the massive company Carillion is having an effect on a wide range of local facilities and projects. These range from services they run at Southmead Hospital for North Bristol NHS Trust to local construction projects like the Carillion site at Westerleigh Road, Yate near Chedworth - the project to stabilise the bankment on the railway line that runs from Bristol Parkway north towards Yate and Gloucester.

All of the hospital facilities are open as normal and patient appointments are not affected, but the effect on the target date for the rail embankment works is not yet known.

As far as we know the electrification of the main GWR line is not affected, as this is being run by another main contractor.

Update 19/01/2018 - Regarding Westerleigh Rd, Network Rail say: "As far as we’ve been told, Carillion’s work for Network Rail continues for the time being as we work with the official receiver to ensure the continuity of its project work. Our aim is to ensure, as far as possible, that this news won’t impact our projects"

Tuesday, 31 October 2017

Bristol Parkway Upgrade - station AND M4 MOTORWAY weekend closures in November

Update from Network Rail 10/11/2017: "Due to the progress made with our electrification work on the M4 Blue Bridge last weekend, the motorway will not be closed at Junction 19 this weekend (11/12 November) as previously planned.

We will keep you informed of progress with our upgrade works around the Bristol Parkway area which continue this weekend (11/12) and next (18/19) with no trains calling at the station. Please check before you travel at gwr.com/bristol2017 or crosscountrytrains.co.uk"

Network Rail say: "Our work to increase capacity at Bristol Parkway will continue over the first three weekends of November during planned closures of the station"

"The project includes the extension of the three existing platforms and the construction of a fourth to serve GWR’s new fleet of Intercity Express Trains. We’re also improving the track layout to allow more trains to use the station. The new platform is due to come into use in December 2017"

Bristol Parkway Station will be closed as follows:
  • Sat 4 - Sun 5 Nov
  • Sat 11 - Sun 12 Nov
  • Sat 18 - Sun 19 Nov
M4 Motorway closures

Network Rail continue: "To carry out installation of electrification equipment on the blue railway bridge over the M4 motorway we need to shut the road. To limit disruption we are doing this overnight"

The motorway is scheduled to be closed as follows:
  • Fri 3 Nov 11 pm - Sat 4 Nov 7 am
  • Sat 5 Nov 9 pm - Sun 5 Nov 8 am
  • Sun 5 Nov 10 pm - Mon 6 Nov 5 am  
  • Fri 10 Nov 11 pm - Sat 11 Nov 7 am
  • Sat 11 Nov 9 pm - Sun 12 Nov 8 am
  • Sun 12 Nov 10 pm - Mon 13 Nov 5am  
Foundation Piling progress

"We made great progress with the electrification of the railway between Swindon and Patchway during the line closure in August/September. However, we still have a number of foundations to install, along with the electrified overhead line equipment"

"Piling between Patchway and Bristol Parkway stations is taking place every Saturday night until February 2018. Our hours of work will be between 21:00 – 07:00. We will also be making the most of an opportunity to install a number of foundations during the daytime in this area on the 11 and 12 November"

"We also have a number of foundations left to install in the Acton Turville, Chipping Sodbury and Old Sodbury areas"




Filton Abbey Wood Station

"Work is continuing to prepare Filton Abbey Wood for more trains as part of our project to double the number of tracks on the Filton Bank between Bristol Parkway and Bristol Temple Meads.  We will be adding a fourth platform to the station, with ramped access to the existing footbridge"

"To support the embankment, we are currently building a retaining wall between the site of the new platform and the residential area that backs on to the railway. We’ll then return at a later date to extend the three existing platforms and lay the new track"

"Pedestrians approaching the platforms from the car park side are being diverted via Nutfield Grove while the existing footpath is closed until the end of 2017"