Sunday, 22 July 2018

Works near Chedworth - rail clearup has started

The Network Rail works next to Chedworth ground to a halt a while ago when the main contractors Carillion went into bankruptcy. The good news is that Network Rail's new contractor is now on site for the remaining 4 weeks  or so of work, so we hope to see an improvement there soon.

On the project to electrify the main line, the Besom Lane temporary compound just across the footbridge from Shire Way is expected to remain until February 2019.

Monday, 11 June 2018

Works near Chedworth - less mud but rail clearup delayed

We're glad to see that there is visibly less mud on Westerleigh Road from the tipping at Beech Hill Farm. The road is generally being kept pretty clear, though there have been occasional lapses.

On the Chedworth side the Network Rail works are still at a standstill following main contractors Carillion going into bankruptcy. The good news is that Network Rail have appointed a contractor for the remaining 4 weeks work, so we hope to see an improvement there soon.

On the the project to electrify the main line, the Besom Lane temporary compound just across the footbridge from Shire Way is expected to remain until February 2019.