Bristol Parkway Upgrade - station AND M4 MOTORWAY weekend closures in November
Update from Network Rail 10/11/2017: "Due to the progress made with our electrification work on the M4 Blue Bridge last weekend, the motorway will
not be closed at Junction 19 this weekend (11/12 November) as previously planned.
We will keep you informed of progress with our
upgrade works around the Bristol Parkway area which continue this
weekend (11/12) and next (18/19) with no trains calling at the station.
Please check before you travel at gwr.com/bristol2017
or crosscountrytrains.co.uk"
Network Rail say: "Our work to increase capacity at Bristol Parkway will continue over the first three weekends of November during planned closures of the station"
"The project includes the extension of the three existing platforms and the construction of a fourth to serve GWR’s new fleet of Intercity Express Trains. We’re also improving the track layout to allow more trains to use the station. The new platform is due to come into use in December 2017"
Bristol Parkway Station will be closed as follows:
- Sat 4 - Sun 5 Nov
- Sat 11 - Sun 12 Nov
- Sat 18 - Sun 19 Nov
Network Rail continue: "To carry out
installation of electrification equipment on the blue railway bridge
over the M4 motorway we need to shut the road. To limit disruption we
are doing this overnight"
The motorway is scheduled to be closed as follows:
- Fri 3 Nov 11 pm - Sat 4 Nov 7 am
- Sat 5 Nov 9 pm - Sun 5 Nov 8 am
- Sun 5 Nov 10 pm - Mon 6 Nov 5 am
Fri 10 Nov 11 pm - Sat 11 Nov 7 amSat 11 Nov 9 pm - Sun 12 Nov 8 amSun 12 Nov 10 pm - Mon 13 Nov 5am
"We made great progress with the electrification of the railway between Swindon and Patchway during the line closure in August/September. However, we still have a number of foundations to install, along with the electrified overhead line equipment"
"Piling between Patchway and Bristol Parkway stations is taking place every Saturday night until February 2018. Our hours of work will be between 21:00 – 07:00. We will also be making the most of an opportunity to install a number of foundations during the daytime in this area on the 11 and 12 November"
"We also have a number of foundations left to install in the Acton Turville, Chipping Sodbury and Old Sodbury areas"
Filton Abbey Wood Station
"Work is continuing to prepare Filton Abbey Wood for more trains as part of our project to double the number of tracks on the Filton Bank between Bristol Parkway and Bristol Temple Meads. We will be adding a fourth platform to the station, with ramped access to the existing footbridge"
"To support the embankment, we are currently building a retaining wall between the site of the new platform and the residential area that backs on to the railway. We’ll then return at a later date to extend the three existing platforms and lay the new track"
"Pedestrians approaching the platforms from the car park side are being diverted via Nutfield Grove while the existing footpath is closed until the end of 2017"
No comments:
Post a Comment