Sunday, 6 March 2016

Bridge near Chipping Sodbury School - major works coming

Do you use the Dodington Road bridge near Chipping Sodbury School? Do you realise that it will be closed for a couple of weeks later this year?

At the Frome Vale Area Forum, Network Rail gave a brief update on their plans for increasing the height of the parapets on the railway bridge on Dodington Road, near Chipping Sodbury School.

The bridge will be closed to vehicles from 23 May to 5 June 2016 to enable them to safely carry out the work. This will followed by a series of Saturday night closures, on 28th May, 4th, 11th, 18th and 25th June and 2nd July. A pathway will be kept open for pedestrians and cyclists - we don't know about horses yet.

Network Rail are holding a drop-in for you to ask questions from 4pm – 8pm on Tuesday 15 March in Chipping Sodbury Town Hall.

At the meeting local councillors once again challenged the Network Rail representatives on how the increased height will impact on visibility for motorists and suggested they should explore alternative options. However, subject to approval of the materials for the top section of the parapet extensions they have permission to carry out the work. Claire Young also raised the question of whether it was appropriate for the official diversion to go down Dodington Lane. Officers agreed to look into this.

No comments: